Cliffs PavilionMDE Power supplied and installed a full panel board replacement complete with UKPN liaison and scheduled shutdowns of the main intake supply to enable the replacement of the original 1960’s panel board, although full refurbishment of the property was carried out in the 90’s the existing panel board was retained and extended. During the 2020 Covid pandemic we took on the project to remove the old panel and relocate all services to a bespoke panel board that was delivered and assembled on site.